The Impact Assessment Act gave Ottawa the power to designate projects for federal review. The Supreme Court of Canada found that scheme partly unconstitutional in 2023, Ottawa amended the Act in 2024, and it now presents streamlining as a federal discovery. That sequence is the story of the Act.
Key facts
- Bill C-69, which enacted the Impact Assessment Act, was introduced in the House of Commons on February 8, 2018 and received royal assent on June 21, 2019, according to the Parliament of Canada.
- The Supreme Court of Canada ruled on October 13, 2023 in Reference re Impact Assessment Act (2023 SCC 23) that the designated projects scheme exceeded federal jurisdiction, as set out in the Supreme Court of Canada decision.
- The Major Projects Office launched on August 29, 2025 with its main base in Calgary and a target of a maximum of two years for approvals of projects of national interest, according to the Prime Minister of Canada.
- The Alberta Court of Appeal held on October 9, 2026 that the amended Impact Assessment Act remains unconstitutional, according to a Government of Alberta statement.
How the Act Got Here
Bill C-69 was introduced in February 2018 and received royal assent in June 2019. It replaced the former Canadian Environmental Assessment Act with a broader, more unpredictable regime that gave Ottawa sweeping authority to designate projects for federal review. The uncertainty that followed was not theoretical. Proponents deferred investment decisions. Capital moved. Alberta’s energy sector bore the sharpest edge of that uncertainty.
Alberta referred the legislation to the courts. In October 2023 the Supreme Court of Canada found that the federal scheme for designated projects was partly unconstitutional, ruling that core provisions intruded on provincial jurisdiction. Ottawa responded with amendments that came into force in June 2024, narrowing the definition of reviewable effects to focus on areas of clear federal jurisdiction and strengthening language around provincial substitution.
The Major Projects Office Changes the Picture
The more significant shift came in August 2025, when the federal government launched the Major Projects Office under the Building Canada Act. Headquartered in Calgary, the MPO is tasked with coordinating regulatory approvals across departments for projects of national interest, with a stated target of completing assessments within two years. Projects designated under the Building Canada Act are exempt from certain Impact Assessment Act provisions, and standard IAA timelines do not apply to them.
That is a meaningful change from the open-ended timelines that defined the C-69 era. The principle is one project, one review, with the MPO serving as a single point of contact for proponents, investors, and other levels of government. Dawn Farrell, the former TransAlta chief executive, leads the office. She is not a bureaucrat who needs convincing that project timelines matter.
In March 2026, Canada and Alberta reached an agreement-in-principle for a one project, one review approach to major infrastructure. A formal Co-operation Agreement on Environmental and Impact Assessment followed in April 2026. On October 1, 2026, the west coast oil pipeline, now called Pacific Link, was listed as a project of national interest under the Building Canada Act, according to the Government of Alberta. The Major Projects Office is to work with the Canada Energy Regulator on a streamlined review, with a conditions document due by September 1, 2027. Under the 120-day approval framework the province itself has been building out, Alberta has positioned itself to meet Ottawa partway on timelines.
What Approval Certainty Actually Means
The business case for major resource and infrastructure projects rests on predictable timelines. A proponent accepting a billion-dollar capital commitment needs to know when a decision will come, not simply that one will eventually arrive. For most of the C-69 era that certainty was absent. Projects were not necessarily rejected outright. They were delayed, subjected to expanding scope, and ultimately priced out of the investment queue.
Alberta’s pipeline, mining, and transmission projects represent the clearest test of whether the new architecture delivers. The MPO’s two-year timeline, if honoured, would mark a genuine improvement over what preceded it. Whether that timeline holds under political pressure, and whether the Co-operation Agreement with Alberta produces consistent outcomes, will take years to confirm.
The Score Ottawa Owes
Credit where it is due: the federal government has moved further on regulatory reform in the past twelve months than in the previous decade. The IAA amendments, the Building Canada Act, the Alberta Co-operation Agreement, and the pipeline deal framework are all steps in the right direction. But they follow years of approvals uncertainty that cost Alberta real investment, real jobs, and real export capacity.
The federal government discovered that long review timelines deter capital because the courts said so, because the provinces pushed back, and because a global trade environment now makes Canadian energy exports look like an asset rather than an inconvenience. That sequence matters. Ottawa is catching up on regulatory reform.
Update, October 9, 2026. The Alberta Court of Appeal held that the amended Impact Assessment Act remains unconstitutional, according to a Government of Alberta statement. Alberta referred the amended Act to the court in November 2024, and the statement does not say which provisions fall.
Pacific Link is the first real test of the new architecture. It was listed on October 1, 2026, and the conditions document is due by September 1, 2027. The direction is right. The follow-through still has to be shown.




