Eight years. That is the expected life of the artificial turf laid at McMahon Stadium in 2025, according to the McMahon Stadium Society, and it puts a date on the talk that the 113th Grey Cup could be the last one the building hosts.
Society chair Steve Allan has said the society does not intend to lay turf in the building again. That makes the start of the 2033 season the working target for a new home for the Calgary Stampeders. No replacement has been approved. No government or team has committed money to build one.
Key facts
- McMahon Stadium opened in 1960 on University of Calgary land and is operated by the McMahon Stadium Society, according to the University of Calgary Dinos.
- The City of Calgary issued Request for Proposal 26-1556 for feasibility and strategic advisory services on a major sports and events facility, with bids closing June 16, 2026, according to the CanadaBuys tender notice.
- The Edmonton Elks and the Montreal Alouettes played the 113th Grey Cup at McMahon Stadium in Calgary on Nov. 15, 2026, according to the Canadian Football League.
- The grandstand at GMC Stadium on Stampede Park seats 17,000, according to the Calgary Stampede.
A turf surface sets the clock for the whole building
Artificial turf is a wear part. The fibres flatten, the infill migrates and the pad underneath breaks down with every season of games and practices. When a surface reaches the end of its life, the owner has two choices. It buys another one, which commits the stadium to roughly another eight years of operation, or it stops. Allan’s position is that the society stops after this one. A maintenance line has become the schedule for a capital decision.
The rest of the building is ageing on the same schedule. Allan has said the society spent close to $1 million this past summer on the stadium’s sewage and water system, work he described as needed to keep the building safe to operate through the Grey Cup. In November he called McMahon tired and said it is time for a new building.
Three organizations are studying the same problem from three sites
The City of Calgary is paying for advice. Its tender, RFP 26-1556 on CanadaBuys, asked firms to assess the feasibility and planning of a major sports and events facility, and the study has been reported at an estimated $875,000. The city has also said it is working with the university and the society to keep McMahon operating safely in the meantime.
The Calgary Stampede has hired a firm to study whether field sports could be added to GMC Stadium, and it hopes to have an answer by summer 2027. The University of Calgary, which owns the land under McMahon and fields the Dinos football team there, has raised about $23 million toward a 5,000-seat campus stadium of its own. Three studies. One tenant that needs a field by 2033.
The money question has not been put on the table
By Alberta Tribune’s count, the gap between the Stampede’s hoped-for answer in summer 2027 and a first regular-season game in June 2033 is about six years. That window has to hold financing, design, approvals and construction. Calgary has already watched another older venue need structural attention, in the Saddledome roof and its cable net. The Grey Cup crowd also saw the Snowbirds fly the CT-114 Tutor over Calgary for a final time, and Stampede Park is already planning around the 2027 Calgary Stampede.
By Alberta Tribune’s count, the gap between the Stampede’s hoped-for answer in summer 2027 and a first regular-season game in June 2033 is about six years. That window has to hold financing, design, approvals and construction. Calgary has watched long stadium and arena talks before, including the debate the city lived through around who pays for growth through off-site levies. The Grey Cup crowd this week also saw the Snowbirds fly the CT-114 Tutor over Calgary for a final time, and Stampede Park is already planning around the 2027 Calgary Stampede.
Summer 2027 for the Stampede’s answer on GMC Stadium. June 2033 for the first game on whatever surface replaces McMahon’s.