Under the Expedited 120-Day Approvals Act, Cabinet can designate a qualified project, list every approval it needs and start a 120-day clock for the regulators on that list. The act sets when a decision is due. Each decision itself still belongs to the regulator.
Key facts
- The act began as Bill 30 and passed on May 6, 2026, according to the province.
- A project first has to be approved for qualified designation.
- Once it is, Cabinet issues an Order in Council that lists every approval the project needs and starts a 120-day clock for regulators.
- As tabled, the bill pointed at major energy, mining and industrial projects over $250 million in capital spending.
- Law firm analysis of the bill reads the deadline as 120 business days, and says it requires a decision, not an approval.
How the clock works
The Order in Council is the trigger. Before it, nothing is on a deadline. After it, regulators have to decide on each listed approval inside the window. That is the whole design, and it is a short one.
One note on the math, and the arithmetic is Alberta Tribune’s own. If the window is 120 business days, as commentators read the bill, that is about 24 working weeks, or a bit under six months. If it were calendar days it would be four. The province’s public page says 120 days, so projects should read the order itself.
What the act does not do
A deadline on a decision is not a guarantee of a yes. Legal commentary on the bill is clear that regulators still have to decide, and may refuse. The harder design question is how a fixed clock fits projects that need a public hearing, where fairness rules set their own pace. That is a program question, and the first few orders will answer it.
Once Cabinet signs an order for a designated project, each regulator named in it owes the project owner a decision inside the window that order sets.
Sources
- Government of Alberta, Accelerating major project approvals (alberta.ca).
- Borden Ladner Gervais LLP, analysis of Bill 30.
- McCarthy Tétrault, Bill 30 and what it means for the energy sector.
- ABlawg, commentary on Bill 30 and the 120 business day decision window.