The Alberta Utilities Commission did something this month that does not happen often. It told an entire town it would be heard. In a June 16 ruling, the regulator granted intervener standing to more than 680 people in Olds and threw out its usual rule that limits formal participation to those living within 2,000 metres of a project. For the proposed data centre and power plant on the edge of town, anyone who lives in Olds now has a seat at the table. That is not a roadblock. That is the process doing exactly what it should.

The same week, the Commission hit pause. It suspended the proceeding until Synapse answers a second round of questions, after an earlier set sent in May went to turbine specifications, diesel fuel storage, job creation, and wetlands management. The company sent responses on June 5. The regulator read them and decided it still needed more before the file could move. So the clock stops until the answers arrive.

This is the second time the homework was incomplete

It is worth remembering how the project got here. Back in March the Commission closed Synapse’s first application outright, ruling it did not meet the minimum standard to even begin a formal review. The company reapplied in April. Now the second attempt is stalled on the same basic problem, which is missing information. This is a proposal to build what would be the largest data centre complex in the country, paired with a 1,400 megawatt natural gas plant to feed it. A development on that scale draws power on the order of a small city. If the people behind it are struggling to file a complete application twice in a row, it is fair to ask whether they are ready to build and run infrastructure this big next to a town of ten thousand people.

Hard questions are not anti-investment

There will be a temptation to read all of this as Alberta getting in its own way, scaring off capital with red tape while the province says it wants up to 100 billion dollars in data centre investment. That reading is backwards. Diesel storage, turbine emissions, water and wetlands, and whether the promised jobs actually show up are not trivia. They are the exact things a community deserves straight answers on before a project like this breaks ground. A regulator that demands them is not the enemy of growth. It is the reason a deal, once approved, can actually stand.

- Advertisement -

We have argued before that the AI boom should not steamroll rural Alberta, and this is what the alternative looks like in practice. The town did not stop the project. It showed up in numbers, the regulator widened the door to let it in, and the proponent now has to prove its case. That is local consent working through the system rather than around it.

A serious province acts like one

Alberta has spent years building a real advantage in this industry while other governments wrote announcements. The way to keep that advantage is to be the jurisdiction where good projects move fast because the rules are clear and the reviews are credible, not the one where anything gets waved through and the cleanup comes later. Serious investors can tell the difference. So can the families who will live beside whatever gets built.

The Olds project may still be a good one. The town could end up with jobs, investment, and a landmark in the new economy. But it has to clear the bar first, and the bar is not unreasonable. Answer the questions. Show the work. Earn the approval. If Synapse can do that, Alberta gets a win it can defend. If it cannot, the pause will have told us something important before a shovel ever hit the ground.

If a company cannot file a complete application twice, should that make us more cautious about handing it the largest data centre in the country?

Share This Article
Follow:
Alberta Tribune is an independent Alberta news and opinion publication based in Calgary. This is the editorial desk byline, used for reporting and commentary produced by the newsroom on Alberta politics, energy and pipelines, business, infrastructure, agriculture, artificial intelligence and provincial public policy.
Leave a Comment