How close is too close? Two kilometres northwest of Indus, Beacon AI Centers wants to build a natural gas power plant with up to 1,494 megawatts of generating capacity, most of it earmarked for a data centre campus next door.
What Beacon Is Actually Proposing
The plant would supply roughly 1.2 gigawatts to on-site AI and high-performance-computing data halls, built in four blocks of about 300 megawatts each, with the remainder covering plant and site operations. Water use is where the project draws the sharpest questions. Beacon’s own filings put the campus at up to 1.5 million litres of municipal water a day, close to 1,500 cubic metres, with roughly half of that tied to the power plant and site operations alone.
Public submissions to the Alberta Utilities Commission have raised concerns about water, noise, traffic, farmland and the general character of a rural area suddenly hosting industrial-scale power generation. Some residents commenting on the project publicly have asked why the plant cannot run closed loop with all its cooling water recovered and reused, rather than drawing new municipal supply.
The Process So Far
The project has already cleared two hurdles. Rocky View County approved the municipal side of the file back in June 2025. Ottawa determined in March 2026 that the project needs no further federal Impact Assessment Act review, though that determination does not itself authorize construction.
The remaining hurdle is the one that matters most for how the plant actually operates. The Alberta Utilities Commission held its hearing on the thermal power plant application from August 18 to 21, and as of this week no decision has been issued. Construction permits still need to follow whatever the AUC decides. Alberta has already shown this year that a hearing does not guarantee approval, having rejected a similarly framed gas plant proposal near Olds after more than 1,500 public filings.
What Neighbours Still Do Not Know
Alberta wants the investment a project like this represents. Rural communities still have to live beside the infrastructure it brings, long after the hearing transcripts are filed away. A project of this size only earns durable community support if residents get specific, binding answers on water sourcing, noise limits and distance from existing homes, not general assurances that get finalized after the plant is already under construction.
If Beacon’s project supplies its own power rather than drawing off the shared grid, that changes some of the calculus around fairness to other ratepayers. It does not change the calculus for the people who will hear it, see it and live next to its water use every day.
If a project like this supplies its own power, where should Alberta draw the line on size, water use and distance from existing communities?